FRANKLIN- RECONSTRUCTION ON KING STREET AND I-495 RAMPS
This is a safety and traffic improvements project. It extends along King Street from Union Street to Upper Union Street and also includes Upper Union Street from King Street to Constitution Boulevard and all four I-495 ramps at King Street. It involves roadway improvements as well as intersection signalization improvements.

Project includes widening of King Street to provide two lanes in each direction with left and right turning lanes at appropriate locations; widening and realignment of Upper Union Street to make Constitution Boulevard the major traffic movement; upgrading the signals at the King and Upper Union Street intersection and providing two left turn lanes from King Street onto Upper Union Street.

New signals will be installed at the intersections of I-495 southbound and northbound ramps, and the signals at the King and Union Street intersection will be upgraded. The signals along King Street will be synchronized to provide better traffic flow along King Street.

Existing concrete pavement will be removed from all four I-495 ramps and ramps will be reconstructed with full depth asphalt pavement. In addition, project involves drainage improvements, curbing, new sidewalks, wheelchair ramps, pavement markings, signing, landscaping, a closed circuit television camera for traffic monitoring on I-495, and other incidental work. This project will require temporary and permanent easements for its implementation.
You can find this on the MassHighway web site here. Select Franklin to see the current project status. Project 602962. By the way, it also shows completed projects.