Downtown Project: Update #3


The contractor is finishing up placing drainage structures in the Downtown this week. 
They are also working in front of Dean College on drainage. Next week they will begin to bring on another crew and start reclaiming at the intersection of Pleasant and Main Street and work toward Dean College. 
They are still planning to bring in a small crew to install street light bases in about 50 locations.  They anticipate they can install four or five light bases a day so it will take 2 to 3 weeks once they begin. 
If anyone has a question, please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer Michael Maglio at 508-553-5500 or my office at 508-520-4949.
it is quiet on Main St early in the morning
it is quiet on Main St early in the morning


-------------------------------------------------------

This email is intended for municipal / educational use only and must comply with the Town of Franklin and Franklin Public School's policies and state/federal laws. Under Massachusetts Law, any email created or received by an employee of The Town of or Franklin Public Schools is considered a public record.  All email correspondence is subject to the requirements of M.G.L. Chapter 66. This email may contain confidential and privileged material for the sole use of the intended recipient. Any review or distribution by others is strictly prohibited. If you are not the intended recipient please contact the sender and delete all copies.

No comments:

Post a Comment