Friday, June 24, 2016

Downtown Project Update #37

Work Schedule for the week of June 27 to July 1. 
The Contractor will be milling for crosswalks only beginning at the intersection of Main/Pleasant St. Sunday night and Monday night. 
The Contractor is scheduled to pave Wednesday night and Thursday night. The area they plan to pave will be East Central St, the small section of West Central St and any additional area on Main St we can get to. We will be able to keep at least one lane open so there will be no major detours. 
There will be no night work Tuesday night. 
Please contact the Town Administrator's Office at 520-4949 with any questions. We will continue to keep the public informed through our website, Twitter and Facebook.