"Unforeseen conditions have delayed the renovation project at the Franklin Senior Center, though officials hope the lag will not be too lengthy.
The center is in the middle of a $1 million project to finish the building's second floor. 
Deputy Town Administrator Jamie Hellen said that it was conditions at the site itself that caused the problem. 
"When digging the hole for the elevator shaft, they hit rock," he said. "They had to go back into the plans and move the elevator shaft a little bit."

Continue reading the article online (subscription may be required)
http://www.milforddailynews.com/news/20161108/franklin-senior-center-project-slowed