Beaver Street Interceptor: Construction Updates for week of June 17 - June 21

 
Beaver Street Interceptor (BSI) Construction Update 
for the Week of June 17th!

Monday (6/17) - Friday (6/21) the construction crew will be moving over to Rt. 140 at Grove Street to start construction of the new sewer main that will be crossing from Grove St, through Rt. 140 onto West Central Street. Expect lane closures on Rt. 140 at the Grove Street intersection as this work progresses.  

Also, there will be a limited crew working inside sewer manholes on Old West Central from Pond Street to Tri-County Drive (behind Starbucks).  Only lane shifts might be required and access to the adjacent medical buildings and residences along this area will not be impacted.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue this week. There is a new way in and out of the Recreation Center, please follow the posted signage. During times of drop off and pickup backup onto Beaver Street may occur.

logo

Please reference the interactive map below and posted signs for details and updates.

Beaver Street Interceptor: Construction Updates for week of June 17 - June 21
Beaver Street Interceptor: Construction Updates for week of June 17 - June 21

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov

Beaver Street Interceptor Rehabilitation/Replacement Project
This project consists of the replacement and repair of Franklin's largest piece of sewer infrastructure,
originally constructed in 1914.

Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor