Beaver Street Interceptor BSI Construction Update 

for the Week of September 23!

Monday (9/23) -  Friday (9/27): The construction crew will be working on West Central St between Rt 140 and Forge Pkwy between the hours of 7am-4pm.  West Central St will be closed in both directions.  Please follow posted detour signs for directions.

Monday (9/23) - Friday (9/27): There will also be a construction crew working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm.  Grove Street will be open and reduced to a single lane.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation.

Please reference the interactive map below and posted signs for details and updates.

Beaver Street Interceptor (BSI) Project: Construction update for week of 9/23 - 9/27
Beaver Street Interceptor (BSI) Project: Construction update for week of 9/23 - 9/27

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
 

This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.

Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe
here (select Beaver Street Interceptor from the list).

Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project


No comments:

Post a Comment