Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of October 21st!
Monday (10/21) - Friday (10/25): There will be a construction crew working in the area of 257 Fisher Street. All construction work will be off the road in a wooded easement and work will occur between the hours of 7am-4pm. No traffic impacts are expected.
Also, Monday (10/21) - Friday (10/25): A second construction crew will be working on Old West Central Street connecting the existing sewer service laterals to the new sewer main. Please follow detour signs as the traffic pattern will change.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation. On Friday October 25th, a large concrete pour is scheduled, limited traffic impacts are expected on Beaver Street during this time.
Please reference the interactive map below and posted signs for details and updates.
Beaver Street Interceptor (BSI) Project - Construction update for week of Oct 21 to 25, 2024
We appreciate the public's continued support and understanding and will continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914.
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
No comments:
Post a Comment