via DPW posting:
"Phase 8 - Sewer Lining Project Continues Monday March 24th thru April 9th.Below is the anticipated schedule for the Sewer Lining work that National Watermain will be conducting:3/24 – 3/28: start grouting services (Pine Street, Stanwood Drive, Mary Anne Drive)3/31 – 4/4: Continue grouting services4/3 – 4/4: Complete Lining along Pine St4/7 – 4/9: Lining Easement Beech St to Mary Ann DrivePlease follow posted detour signs and use caution when driving in these areas.During this part of the lining residents that will be directly affected will be notified. If you experience any issues please call the DPW at 508-553-5500.This work will help to improve the structural integrity of our sewer system and reduce groundwater intrusion which reduces our bill from the Charles River Pollution Control District.
For a virtual representation of the service line grouting process check out this video - https://www.youtube.com/watch?v=F2oqgS0W9ew"