Monday (3/31) through Friday (4/4): The construction crew will be conducting the jack and bore trenchless installation of the new sewer under Rte. 140. The work will be occurring off the road at 38 Pond St. and within the Franklin Village Mall area. No traffic impacts are expected.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation of the launching chamber, civil work within the site, and mechanical work within the pump room. On Friday April 4th, the delivery and setting of the launching chamber will take place. No traffic impacts are expected but access to the Franklin Recreation building will be limited.
![]() |
Updates to Beaver St. Interceptor Project |
Please reference the interactive map and posted signs for details and updates.
We appreciate the public's continued support and understanding and will continue to communicate regularly via social media, our dedicated email list, and the construction map as work progresses.