GROVE STREET ROAD CLOSURE NOTICE!!
Starting Monday (5/5) Grove Street will be closed at the MBTA train tracks between the hours of 7 AM and 4 PM. Then on Tuesday (5/6) starting at 7 AM the area will be closed 24 hours a day until Friday (5/9). This full time closure is needed for the installation of the sewer main under the train tracks.
![]() |
Beaver St. Interceptor Project |
The contractor will also be working off the road at 38 Pond Street, Franklin Village Mall and at 260 Fisher Street. This work will happen throughout the week and limited to no traffic impacts are expected.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with preparation for the masons to be onsite to construct the exterior building structure.
For additional info on the project -> https://ma-franklin.civicplus.com/557/Beaver-Street-Interceptor-BSI-Project