RT. 140 (West Central Street) Lane Closure Alert 7 PM to 5 AM:

Beaver Street Interceptor (BSI) Project Construction Updates
Beaver Street Interceptor (BSI)
Project Construction Updates
Sunday night, October 5, the Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. In addition, the Contractor will be conducting pipe fusing operations on Old West Central from Tri-County to Franklin Crossing.

During this time there will be evening lane closures on RT. 140 from 7pm to 5am. Please use caution when traveling in this area and follow all posted signs. Note that this work is expected to continue from Sunday night through Thursday morning for the next 6 to 8 weeks. 

In addition, on either Tuesday (10/7) or Wednesday (10/8) night it is anticipated that access to the Taco Bell will be blocked starting at 8pm to allow for the laydown of pipe across their driveway. 



Beaver Street Pump Station:

On Tuesday 10/7, Eversource Gas will be digging across Beaver Street into the Pump Station Site. There will be a lane closure during this time. Please use caution when traveling in this area and follow all posted signs.

During the week the construction of the new Beaver Street Interceptor Pump Station will continue with work on the exterior building structure and internal building component installation. In addition, the contractor will start the final site work of paving and grading.