Beaver St. Interceptor Project: Construction Updates ~ Monday (3/29) Through Thursday (4/2)

RT. 140 (West Central Street) Lane Closure Alert: Sunday Night (3/29) through Wednesday Morning (4/1), 7 PM to 5 AM and Thursday (4/2) 7 AM to 3 PM

Beaver St. Interceptor Project
Beaver St. Interceptor Project
The Contractor will continue installing the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.

Beaver Street Pump Station

At the Franklin Recreation Center, construction of the new Beaver Street Interceptor Pump Station will continue with the installation and testing of internal building components and pumps.  Access to the recreation center will NOT be affected during this time.