Sunday, March 23, 2025

Sewer lining project continues with Phase 8 - March 24 through April 9, 2025

via DPW posting:
"Phase 8 - Sewer Lining Project Continues Monday March 24th thru April 9th.
Below is the anticipated schedule for the Sewer Lining work that National Watermain will be conducting:
3/24 – 3/28: start grouting services (Pine Street, Stanwood Drive, Mary Anne Drive)
3/31 – 4/4: Continue grouting services
4/3 – 4/4: Complete Lining along Pine St
4/7 – 4/9: Lining Easement Beech St to Mary Ann Drive
Please follow posted detour signs and use caution when driving in these areas.
During this part of the lining residents that will be directly affected will be notified. If you experience any issues please call the DPW at 508-553-5500.
This work will help to improve the structural integrity of our sewer system and reduce groundwater intrusion which reduces our bill from the Charles River Pollution Control District.  
For a virtual representation of the service line grouting process check out this video - https://www.youtube.com/watch?v=F2oqgS0W9ew"

Thursday, February 27, 2025

Phase 8 - Sewer Lining Project Starts Tuesday March 4, 2025

Below is the anticipated schedule for the Sewer Lining work that National Watermain will be conducting:
  • Phase 8 - Sewer Lining Project Starts Tuesday March 4, 2025
    Phase 8 - Sewer Lining Project
    Tuesday (3/4) – Pine Street (#161/152 to #169/170), Stanwood Drive (Pine St to #39/36)
  • Wednesday (3/5) – Stanwood Drive (#8/11 to #20/31), Pine Street (#80/81 to #102/103)
  • Thursday (3/6) – Pine Street (#102/103 to #152/151)
  • Friday (3/7) – Pine Street (Mary Ann Dr to #80/81)
  • Monday (3/10) – Mary Ann Drive (#9/10 to Pine St), Pine St (Mary Ann Dr to #9/28)
  • Tuesday (3/11) – Pine Street (#9/28 to Pond St)
Please follow posted detour signs and use caution when driving in these areas.

During this part of the lining residents that will be affected will be notified. If you experience any issues please call the DPW at 508-553-5500.

This work will help to improve the structural integrity of our sewer system and reduce groundwater intrusion which reduces our bill from the Charles River Pollution Control District.