As I got to the train station this morning, I realized the paving had not been done over night as scheduled.
![]() |
The corner of Emmons and West Central |
Fortunately, I did find this update on the Franklin webpage to explain the situation:
"The Hot Mix Asphalt Plant that Walsh uses (Pawtucket Asphalt) had a major mechanical failure and will not be operational until tomorrow morning. We are moving our paving operations to Thursday night.
If anyone has a question, please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at 508-520-4949."