Community Closet Closed Today, Tuesday, April 28 due to construction
Saturday, April 25, 2026
Beaver St. Interceptor Project: Construction Updates ~ Sunday (4/26) Through Friday (5/1)
Monday, April 20, 2026
Beaver Street Interceptor (BSI) Project: Construction Updates ~ Monday (4/20) Through Friday (4/24)
Tuesday, April 14, 2026
South Station Air Rights Project: Rail and Bus Terminal Connection is Now Complete !!!
|
Sunday, April 12, 2026
Beaver St. Interceptor Project: Construction Updates ~ Sunday (4/12) Through Friday (4/17)
Saturday, April 4, 2026
Road construction alert for Saturday: King St & Constitution Blvd
Saturday, March 28, 2026
Beaver St. Interceptor Project: Construction Updates ~ Monday (3/29) Through Thursday (4/2)
![]() |
| Beaver St. Interceptor Project |
Saturday, March 21, 2026
Beaver St. Interceptor Project: Construction Updates ~ Monday (3/23) Through Friday (3/27)
Saturday, February 28, 2026
Beaver St. Interceptor Project: Construction Updates ~ Monday (3/2) Through Friday (3/6)
The Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the internal building component installation and testing of the pumps. Bypass piping equipment will be onsite and protected by barriers. Access to the recreation center will NOT be affected during this time.
Visit the project page for additional info - https://ma-franklin.civicplus.com/557/Beaver-Street-Interceptor-BSI-Project
Saturday, February 14, 2026
Beaver Street Interceptor (BSI): Project Construction Updates ~ Monday (2/16) Through Friday (2/20)
The Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.
Beaver Street Interceptor (BSI)
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the internal building component installation and testing of the pumps. Bypass piping equipment will be onsite and protected by barriers. Access to the recreation center will NOT be affected during this time.
Wednesday, February 11, 2026
Franklin United Methodist Church construction begins on foundation for their addition
Saturday, January 31, 2026
Beaver Street Interceptor (BSI) Project: Construction Updates ~ Monday (2/2) Through Friday (2/6)
- At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the internal building component installation and testing of the pumps. Bypass piping equipment will be onsite and protected by barriers. Access to the recreation center will NOT be affected during this time.
Saturday, January 24, 2026
Beaver Street Interceptor (BSI) Project: Construction Updates ~ Monday (1/26) Through Friday (1/30)
![]() |
| Beaver Street Interceptor (BSI) Project |
Saturday, January 17, 2026
Beaver St. Interceptor Project: Construction Updates for Week of Jan 19 to 26, 2026
The Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.
The contractor will be working off the road along Fisher Street. There are no anticipated traffic impacts at this location.
Beaver St. Interceptor Project
As the weather allows the contractor will be working on the installation of the helical piles along the side of West Central Street. During this time there will be evening lane closures on West Central Street. Please use caution when traveling in this area and follow all posted signs.Beaver Street Pump Station
the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the internal building component installation and testing of the pumps. Bypass piping equipment will be onsite and protected by barriers. Access to the recreation center will NOT be affected during this time.
For additional details on the complete project, please visit -> https://ma-franklin.civicplus.com/557/Beaver-Street-Interceptor-BSI-Project
Tuesday, January 13, 2026
Updates to Beaver St. Interceptor Project for week of Jan 12 - 16, 2025
- The contractor will be working off the road along Fisher Street. There are no anticipated traffic impacts at this location.
- At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the exterior building structure, internal building component installation, and final site work.
- No work planned this week
Saturday, January 3, 2026
Beaver St. Interceptor Project: Construction updates for week of Jan 5 - 9, 2026
Thursday, January 1, 2026
Franklin Ridge Begins Construction
After 11 years of groundwork, the affordable senior housing project moves toward construction with an eye toward opening in late 2027
Through the Franklin Municipal Affordable Housing Trust, the Town of Franklin is proud to announce that the Franklin Ridge Senior Housing project has secured all necessary funding and construction-related approvals to commence the construction of this three-story, 60-unit affordable senior housing complex in November. 
Franklin Ridge Begins Construction
Over the past eleven years, the Town of Franklin and Franklin Municipal Affordable Housing Trust have worked closely with JNJUHL & Associates, a local, affordable housing developer, to provide much needed affordable housing for Franklin’s senior community 62 years of age or older. Located adjacent to the Eaton Place senior housing complex, the Franklin Ridge housing development will consist of (54) One-Bedroom Units and (6) Two-Bedroom Units, in addition to community space that includes a community room with a kitchenette, library, a multi-purpose room and offices for management and social service staff.
"With the senior population in Franklin growing exponentially, the Town continues to be committed to providing high quality affordable senior housing which keeps our Franklin seniors within the community for the long-term” stated Town Administrator Jamie Hellen. “Seniors are an essential and valued component of this community, providing not only an important link to our past, but a viable element that continues to make a significant contribution through volunteering as well as supporting town activities and organizations. This project will allow income eligible seniors to right-size their living situation and stay in the community they love”.
With 70% local preference, which is the maximum percentage allowed under state regulation, the Town is focused on getting as many local eligible seniors as possible into the Franklin Ridge Senior Housing project upon its completion in 2027.
Jon Juhl, President of JNJUHL & Associates, continues “this project was truly a community effort: the Franklin Municipal Affordable Housing Trust is providing the land, as well as a significant financial contribution of $500,000 toward the project. The Town is also using over $320,000 in Community Preservation Act funding to leverage millions of dollars in federal and state funding from the Executive Office of Housing and Livable Communities. "
"This affordable housing project could not have been accomplished without the hard work and support of many Town Departments and Committees including the Town Administrator’s Office, Department of Planning & Community Development, Building Department, Conservation Commission and Zoning Board of Appeals; all with one goal in mind: to meet the supportive housing needs of seniors while building a green and sustainable project. Franklin Ridge will be just that: housing which has adaptive, accessible apartments, is 100% electric, and has solar back-up. It is a project that will benefit Franklin seniors –and our community—for many years to come.”
Franklin Ridge Senior Housing Project has been designed for seniors, age 62 and older, who meet income eligibility requirements. Construction will start this winter and occupancy is expected by mid-late 2027. Rental applications will be managed by The Community Builders, a Boston-based non-profit housing development and management company, starting in early 2027. Outreach sessions to the senior center and broader community will begin in 2026.
Saturday, December 13, 2025
Beaver Street Interceptor (BSI) Project Construction Updates ~ Monday (12/15) Through Friday Morning (12/19)
![]() |
| Beaver Street Interceptor (BSI) Project Construction Updates |
Thursday, November 27, 2025
Beaver St. Interceptor Project: Construction Updates ~ Monday (12/1) through Friday (12/5)
![]() |
| Beaver St. Interceptor Project |
Saturday, November 22, 2025
Beaver Street Interceptor (BSI) Project Construction Updates: Monday (11/24) through Tuesday (11/25)
Monday night, November 24 from 7PM to 5AM and Tuesday, November 25 from 8AM to 3PM the Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.
Grove Street will be closed at the MBTA train tracks on Monday 11/24 between the hours of 7am and 4pm.
Traffic turning onto Grove St from Rt. 140 will be detoured over to Beaver Street via Rt. 140. Please follow posted detour signs for directions. The area will be open to Local Traffic only to access the businesses and properties on Grove Street between Forge Hill Road and Rt. 140.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the exterior building structure, internal building component installation, and final site work.
Shared from -> https://ma-franklin.civicplus.com/557/Beaver-Street-Interceptor-BSI-Project