Tuesday, August 20, 2013

"all three options make little sense"

The School Building Committee meeting on Monday heard the presentation from Kaestle Boos Associates on the options for Davis Thayer. Their initial proposal was to add to and renovate the existing facility. They also looked at addressing just the changes needed to make the building compliant with the requirements for accessibility. An alternative would be to start a new building on the existing site (or elsewhere). It was estimated to cost $4.6M to bring to compliance. It was estimated to be $23M to add to and renovate or $28M to build a new school.
Davis Thayer was built in 1924 and underwent an extensive renovation during the 1970s. Milani described the building as "sound." 
"It has good bones," he said. 
However, most of the school’s bathrooms, corridors, stairs and doorways are not handicap-accessible, and inside, there are numerous mechanical and plumbing problems. 
Milani said that just bringing the school into compliance with the Americans with Disabilities Act would cost $4.6 million. The committee mostly agreed that it would not be worth the money. One member described the option as an "expensive Band-Aid."

Read more: http://www.milforddailynews.com/news/x1655328083/Davis-Thayer-renovation-plan-presented-in-Franklin#ixzz2cV2megKq

My notes from the meeting can be found here
http://www.franklinmatters.org/2013/08/live-reporting-school-building.html
http://www.franklinmatters.org/2013/08/live-reporting-davis-thayer-proposal.html

In the News: missing link


'Missing Link' to Upper Charles Trail to be complete next fall

Construction to the "missing link" portion of the Upper Charles Trail has begun on Mt. Pleasant Street behind Sacred Heart Church.


Monday, August 19, 2013

Live reporting - Davis Thayer proposal

The Davis Thayer proposal, hard copy handed out to be added later

Joe Milani, Kaestle Boos Associates
"Feasibility Study for Davis Thayer"

built in 1924, renovated in 1973, minor other adjustments since then

original documents for 1924 construction not available, hence information is based upon what is observed
did an opinion of probable cost (OPC)
did a revision to address if accessibility was addressed but nothing else was

do not have to comply with all elements of the building when reconstruction, do need to fulfill compliance with the sections being addressed

if spending more than 30% of the assessed building value, then do need to bring up to code
staying below this level  intentionally

dangerous situation for walking along the driveway entrance from School St, especially during winter

building in good shape generally but there are spots where there is water penetration through the brick surface; would recommnend repointing all the brick work on the exterior

all the windows were replaced with two circular windows which are still wooden and should be replaced.

roofing in good shape, put on in 2000
stainless steel put over the copper copings along the roof edge, not soldered properly, should be replaced
some downspouts missing from the portable, for any long term renovation, should replace the roof

doors not wide enough to meet compliance, 36" required

interior finishes are pretty good, lots of school work on the walls
suspended acoustical tiles were added in the 1973 renovation, can't see the ceiling clearly

there are asbestos tiles under some of the carpets, would need to be removed

gym floor is is good shape, has signs of water damage, 'Dutchman' repairs evident
recommend putting in synthetic floor

interior stairways; 2 front, 2 back of building
some ramps added to some of the entrances, not all hence not accessible
inside of stairways need additional handrails, stairwells wide enough, hand holds not sufficient

toilet rooms all have accessibility problems
will lose fixtures with renovation but do have enough space to provide sufficient fixtures for accessibility

max population planned for at 350, currently about 335 students

by and large equipment could be reused in renovation, spacing is an issue, need to separate incoming waste and outgoing good foods for safety reasons

water coolers in corridors not sufficient, should provide two levels, there exist only one

no handicap signage available, major crux of issue is elevator brings someone to first floor but other floors within building are not accessible

the building is sound it has sturdy walls

recommend replacement of PA and telephone system

used MSBA recommendation to utilize the space within the building
57200 required
45000 current
renovation and addition would be only option to meet requirements

put the two kindergartens in the 'old' cafeteria
use the first floor expansion to put in a new cafeteria and kitchen area with access from Union
no addition to second floor
elevator and stairwell would go to the basement to access the gym
elevator rises to second and third floor
filled in the media center to provide two more classrooms on the third floor

add parking spaces and a sidewalk from the School St entrance
allows catch basis, rain garden to catch the run off and prevent the current runoff washing out the playground wood chips to the street

$23M for renovation and addition on site; vs. cost of new building on site would be $28M

supplemental study for accessibility
bathroom renovations and addition of elevator
multiple adjustments on each floor

just doing the accessibility = $4.6M

OPC projected a 2.5 year build-out with some inflation

School Committee and Town Council were invited to participate in this review
Other than Tom, no Town Councilor participated

School Committee would need to absorb this info and bring it to the joint budget subcommittee

if this were to go with the new school option, would have to get in line (after the high school)

one of the things that present a problem is that the enrollments are fluctuating, increase since Jul 1, likely to the increase in expectations for the new high school

Planning is meant to increase the attractiveness of the Town

is this site a viable site at all?
there is land but there is a challenge with the existing available land
current space is just under 4 acres, MSBA would req about 10-15 depending upon the size of the school
site big enough for 3-400 but not for 6-800

it is a not starter due to the cost/pupil for renovations vs. new school for this size.

$4M would be a bad band-aid
what to do with the building is not this committee's charge. what to do to construct or renovation may be this committee's charge

This was an informational meeting on the Davis Thayer portion


Live reporting - School Building Committee Meeting - Aug 19, 2013

Present: Tom Mercer, Chris Feeley, Jeff Nutting, Mike LeBlanc, Mike D'Angelo, Maureen Sabolinski, Sally Winslow, Paula Mullen, Susan Rohrbach, Ed Cafasso, Peter Light, Sean Fennell, Cindy Douglas, Corinne Minkle, John Jewel (arrived about 7:00 PM), Bob Gilchrist, Joe Milani,

Meeting opens at 6:35 PM

Motion to approve minutes of July meeting, seconded, approved, passed - unanimous

Motion to approve a series of bills, each seconded, approved, passed - unanimous

Bob Gilchrist, from Agostini, Bacon

walked the group through of three pages of pictures (to be added) showing progress in construction




substantial completion scheduled for July 25, 2014

finish coat of paving will be done next summer so all will be new and fresh
striping this week, signs this week, everything on track for completion on Friday

Brian, FF and E process (furnishing, fixtures and equipment) (if building was turned upside down and shaken, whatever would fall out except for the computers (that is technology).

process started several months ago, approach in two tacks, one with furniture; small working group with furniture; second group on needs for equipment

field trip to Robert Lord showroom for furniture, to see a breath of the possibilities, talking the details of the various vendors and manufacture of the furniture; developed direction, prepared list for each room to determine the quantities required

what is equipment, what is reimbursable from MSBA
received listings from the groups last week, preparing the combination of the lists to see what it would come out at for the budget

more detailed review of the listing planned, planning for putting the FF and E out to bid for Dec/Jan time frame with a July delivery and installation

expecting bids to come in within 2-5% below budget more conservative approach than previous projects

Nutting - we still need to figure out how the studio will be paid for by the cable TV group, or what other option would be needed.

used to be approx $6500/room for FF and E, now running about $8K
varies based upon type of classroom setup

study done by architect showed $1600/per study cost; MSBA reimburses $1200, that is okay for elementary schools but not for the high schools where labs increase the cost

technology is separate from FF and E

Mercer - should have a better idea of the real numbers for FF and E in the next 30-60 days
Sabolinski - Peter Light and others at in with the teachers to take a conservative approach in terms of the needs for FF&E
Light - inventory of existing equipment was starting point, would it last 5 years? yes, or no. If no, then on the listing for replacement. Compiled this at the building level. What was submitted was what the teachers needed with review and aligned with the curriculum. Drove to rationale as required.
Sabolinski - I feel comfortable with the process
Light - some of the teachers spent quite a bit of time and due diligence on this planning process. All of the big ticket areas, visited multiple model schools to discuss the details with those now in the schools

What remains in the building is open for Franklin to keep, what we don't keep can be taken by the contractor as part of the demolition

if there is stuff in good shape, can move it to the new building and deploy it in a non-public space where it can be used but not really observed on a daily basis in a public space; as in the library

Plan for listing of FF and E and budget by the meeting in October, 'no later than' is the plan per Mercer
Desire to get the listing a week before the meeting

all the other model schools were using $1800/student as their target despite the MSBA model target at $1200

Fennell - the high schools are coming in over the $1200 that the MSBA has and I understand the logic and numbers presented.

Change order #3
$40,742
additional electrical  discovered as required
credit for supports not needed
electrical outlets to be added at front of stage
underground manhole to accommodate some wire runs
door hardware
revising door widths, should have been 4' were at 3 something
increased seating capacity in language lab (state standard is 30, added 5 as classes generally run lager)
lecture hall seating change to adjust the riser height

motion made to approve, seconded, passed unanimously

two parking lots built this summer have light poles (actually will), will be wired to new building
need to run lighting to power them in the meantime, could be approx 25-30,000 for the additional wiring and conduit - wouldn't be more than 28K. light pole basis should be ready for end of Sep; it is a safety issue

motion to authorize Chair to approve up to $28K for lighting
seconded, passed unanimously

Nutting - can we add a column to show the MSBA approvals for the change orders as submitted

LeBlanc - when are we going to get the 'pending' items
Is there an opportunity cost to not put the top copy out now?
about 25-29K

Cafasso - question on the parking lots
Both paved lots will get turned over, 120 spaces were on old lot, will get over 300 spaces with what is turned over next week

Question on the grading between the old fields and the new building, and new building and the 'new fields' when the current school goes

switching to the Davis Thayer topic

Fallen Hero: Private Charles E. Mason, U.S. Army

Private Charles E. Mason, U.S. Army Signal Corps, was born on February 24, 1916, son of Fred and Minta Mason. Charles lived at 62 Pleasant Street with his parents and sister. Charles attended the Franklin Public Schools graduating from Franklin High School in 1934. During his high school years, he participated in the Memorial Day ceremonies on the Common by reciting the Gettysburg Address. 
Prior to entering the army, Charles was a member of a Naval Reserve Unit located here in Franklin and served under the command of Fred Cook. David Bullukian, another one of our Fallen 23, also served in this Franklin unit. 
Charles attended Boston Radio and Television School prior to his induction in July of 1941. PVT Charles Mason used this special interest in ham radios and used this skill to converse with people in the area while in the army. 
Private Charles E. Mason died of injuries received in an automobile accident at Fort Monmouth, New Jersey on December 28, 1941 at the age of 25.

FH_Mason
Fallen Hero: Private Mason



For the full series of Fallen Heroes you can visit this link
http://www.franklinmatters.org/2013/08/franklin-fallen-heroes-series.html


Fallen Hero: Ensign William O. Martello, U.S. Navy

Ensign William Olindo Martello, U.S. Navy, was born on April 14, 1920, son of Theresa and Olindo Martelli. Willam was raised by Theresa and her second husband, Nicholas Martello, at 17 Howard Street with his four sisters and one brother. “Willie” attended the Franklin Schools and graduated from Franklin High School in 1937. William went on to Boston University where he graduated with honors with an A.B. degree and was initiated into Phi Beta Kappa. 
William Martello was a student, artist and musician as well as a fighting man. “Willie” was an accomplished concert pianist and was rated as one of the most promising young pianists in New England. Prior to his naval service “Lindy” traveled on the Grace cruise line to South American as an onboard pianist. 
William O. Martello enlisted in the U.S. Naval Reserves on April 17, 1942 and later began his active naval service on April 8, 1943. William O. Martello attended Columbia’s naval officers training program and was commissioned an ensign upon completion of the program on July 28, 1943. He served as second in command aboard an invasion craft off the coast of the Anzio beachhead below Rome. Survivors of Ensign Martello’s landing craft, which had struck a mine in the waters off Anzio, reported that Ensign Martello had refused to heed the order to abandon ship, had fitted out a life raft with provisions, and when last seen, just as the ship turned over and went down, was hurling life belts into the sea for his crewmen swimming in the water. 
A month before his death Ensign William O. Martello wrote to his mother the following lines in a letter to her: 
“As for the war, we had to adjust ourselves to the personal problems it brought, and if a guy can’t take it, then his life is a failure. That is why I am not even afraid of death. If I did one thing that indicated cowardness, the rest of my life would be miserable.” 
Ensign William O. Martello, U.S. Navy, was lost at sea off Anzio on January 26, 1944 at the age of 23.

FH_Martello
Fallen Hero: Ensign Martello


For the full series of Fallen Heroes you can visit this link
http://www.franklinmatters.org/2013/08/franklin-fallen-heroes-series.html



Survey says: Treasurer/Collector should be appointed

The sample size is small (only 15) so this may or may not be a good barometer for how the real ballot question will be answered in November.

Question: Should the Treasurer/Collector position be changed from elected to appointed?
Yes - 9
No - 6

The question opened on August 4 and closed on August 18.