Wednesday, September 2, 2015

Downtown Project Update #9

The proposed work for the week ending 9/5/15 and 9/12/15 will be as follows:

  • Mill transitions on side streets and continue to raise castings and preparation for paving.
  • Paving from School Street to Pleasant Street.
  • Installation of Ballards and finish sidewalk at Dean College pedestrian crosswalk.
  • Complete Boxcut and Binder at Emmons Street and West Central Street.
  • Work on underground (site lighting and signals) at West Central Street and Emmons Street.
  • Begin Curb Installation on West Central Street approximately on 9/10/15.
  • Begin landscaping and seeding on Lincoln Street and Main Street.

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at 508-520-4949. 

sidewalks on West Central at Dean College
sidewalks on West Central at Dean College
This was shared from the Franklin webpage
http://franklin.ma.us/Pages/FranklinMA_News/021E3044-000F8513

No comments:

Post a Comment