Sewer lining project scheduled to continue this week 10/20 - 10/24/25

Sewer lining project scheduled to continue this week 10/20 - 10/24/25
Sewer lining project scheduled to
continue this week 10/20 - 10/24/25
Phase 9 - Sewer Lining Project Starts on Monday October 20th thru October 24th.
Below is the anticipated schedule for the CCTV and cleaning of the sewer work that National Watermain will be conducting:
  • Monday October 20th - Stanwood Drive to Beech Street easement
  • Tuesday October 21st - Sophia Circle to Pond Street easement
  • Wednesday October 22nd - Park Road and Moore Avenue easement
  • Thursday October 23rd - Milliken Avenue to Josephine Street easement
  • Friday October 24th - Chestnut Street to Josephine
Please follow posted detour signs and use caution when driving in these areas.
During this part of the lining residents that will be directly affected will be notified. If you experience any issues please call the DPW at 508-553-5500.
This work will help to improve the structural integrity of our sewer system and reduce groundwater intrusion which reduces our bill from the Charles River Pollution Control District.