Beaver Street Interceptor Project: Construction update for week of Aug 26 - Aug 30, 2024


Beaver Street Interceptor (BSI) Project

 
Beaver Street Interceptor (BSI) Project

Beaver Street Interceptor (BSI) Project

 BSI Construction Update for the Week of August 26!

Monday (8/26) - Friday (8/30) the construction crew will be working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. There will be limited lane closures on Grove Street during this time. Please follow posted detour signs for directions.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation. 

Please reference the interactive map below and posted signs for details and updates.

Beaver Street Interceptor Project: Construction update for week of Aug 26 - Aug 30, 2024
Beaver Street Interceptor Project: Construction update for week of Aug 26 - Aug 30, 2024

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)