Construction Update to Beaver St. Interceptor Project for week of March 24 - 28

Monday (3/24) through Friday (3/28): The construction crew will be conducting the jack and bore trenchless installation of the new sewer under Rte. 140. The work will be occurring off the road at 38 Pond St. and within the Franklin Village Mall area. No traffic impacts are expected.

Construction Update to Beaver St. Interceptor Project for week of March 24 - 28
Construction Update to Beaver St.
Interceptor Project
Monday (3/24): The contractor will be clearing trees/brush along West Central St. and Corporate Drive, one lane road will be in effect with a police detail present. No road closures or detours expected.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation of the launching chamber, civil work within the site, and mechanical work within the pump room.

Please reference the interactive map and posted signs for details and updates.

We appreciate the public's continued support and understanding and will continue to communicate regularly via social media, our dedicated email list, and the construction map as work progresses.

Additional project info can be found on their page -> https://ma-franklin.civicplus.com/557/Beaver-Street-Interceptor-BSI-Project