Continuing on Monday (8/25) thru Wednesday (8/27), Beaver Street will be closed at the MBTA train tracks between 7am to 4pm. Those needing to access 242-290 Beaver Street will be able to do so using Rt. 140 only. This includes access to Franklin Glass, Panera Fresh Dough Facility and Franklin Recreation.
Access to all other locations on Beaver Street, including the Town of Franklin Recycling Center, Beaver Street Recreation Area, and the businesses on Master Drive will be accessed from Grove St. Beaver Street Interceptor (BSI) Project
Starting Thursday (8/28) thru Friday (8/29) the Construction crew will be working off the road on Fisher Street. Limited to no traffic impacts are expected.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the exterior building structure and internal building component installation.
UPCOMING LANE CLOSURE ON RT 140 (West Central Street)
Starting Tuesday, September 2nd, the Contractor will start the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.