Beaver St. Interceptor Project: Construction updates for week of Jan 5 - 9, 2026

Construction Updates ~ Monday (1/5) Through Friday (1/9)

RT. 140 (West Central Street) Lane Closure Alert--
Monday Night (1/5) thru Thursday Morning (1/9) 7PM to 5AM

The Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.

RT. 140 (West Central Street) Lane Closure Alert--
Friday (1/9) 9AM to 2PM

The contractor will be paving the sidewalk on Rt. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.

Fisher Street Easement  - Wednesday (1/7) thru Friday (1/9) - 7AM to 4PM

The contractor will be working off the road along Fisher Street.  There are no anticipated traffic impacts at this location.

Beaver Street Pump Station

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the exterior building structure, internal building component installation, and final site work.