Live reporting - Planning Board/Walgreens

The Planning Board is in the public hearing for the proposed Walgreens at Four Corners. To alleviate traffic concerns, the Town working with Walgreens will add a right turn only lane (north bound on King) to turn onto East Central St (heading east). The second lane will be a combined straight-through traffic (to Chestnut) and left turn (westbound on East Central heading into town).

Jeff Nutting committed that if the applicant provides the design plans by April 1, the town will have enough time to do the work before Walgreens would be scheduled to open (in October).

The public hearing has now been closed. The decision on the special permits required will be scheduled.