DPW roadwork and construction delayed explained

"Because you asked! Installing a new watermain in the "Country Club" neighborhood.  For the most part, the work is going smoothly, however material shortages is slowing the job down. The new water is made of Ductile Iron pipe and it is very short supply due to COVID, which caused the foundry to shut down for a period of time. There is also an increased demand for pipe nationwide because of increased Federal Funding for Public Works projects. 

Two years ago there was no waiting for pipe, now there is wait time of 26 to 40 weeks till the pipe is available.  For example the pipe below was ordered in February,  made in New Jersey on 9/10, delivered to Franklin on 9/16 and started going into the ground on 9/19!

This project was scheduled for next year, as part of the Town's on going "watermain replacement / new roads" program but we were able to use ARPA funding for this work during the current construction season. The old pipe being replaced is made out of asbestos concrete.  

If you would like to know more about water pipe, check out this article:
 



Have a great Public Works Day!"

DPW roadwork and construction delayed explained 1
DPW roadwork and construction delayed explained 1

DPW roadwork and construction delayed explained 2
DPW roadwork and construction delayed explained 2




No comments:

Post a Comment