Beaver Street Interceptor - construction & detours for the week of May 28 - May 31, 2024


Beaver Street Interceptor

 
Beaver Street Interceptor
Beaver Street Interceptor 
 
 

CONSTRUCTION UPDATE WEEK OF MAY 27:

No Work on Monday May 27th - Memorial Day - Remember and Honor those who serve our country!

On Tuesday 5/28/2024, the Contractor will be performing water transfers to the new water main located on Old West Central from Tri County Drive to Dunkin Donuts.  Those residents affected by this will be notified and will have a temporary water service interruption with the potential for no water service to your property between the hours of 7:30 AM and 4:00 PM.

Work will continue on the dead end section of Old West Central serving Ledgewood Condominiums and Franklin Crossing.  Between the hours of 7am to 4pm the dead end section of Old West Central serving Ledgewood Condominiums and Franklin Crossing will continue to be closed at Tri-County Drive.  Those residents should continue to follow the posted signs for directions on exiting and entering. 

Starting Wednesday (5/29), the installation of sewer main on Rt. 140 from Dunkin Donuts towards Wendy's will begin.   This work will occur during the day between the hours of 9am and 3PM.   Expect lane shifts/closures and traffic delays due to active roadwork.

Starting Tuesday night (5/28), the cleaning and lining of the existing Beaver Street Interceptor will be occurring on Cottage Street from Union to Saxon.  

On Wednesday night (5/29), the cleaning and lining crew will be working in the easement between Hayward Street and Beaver Street behind Master Drive. This work will occur at night, during times of low flow, between the hours of 9pm and 5am.  

Work will also continue within the sewer easement between Pond Street and the Brookview Condos.  The cleaning and lining of the existing 24-inch Beaver Street Interceptor is complete and the contractor will be removing the by-pass pump system. Those residents that will be affected by this work have been notified. 

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will begin this week.  There will be a new way in and out of the Recreation Center, please follow the posted signage.  During times of drop off and pickup backup onto Beaver Street may occur. 

Please reference the interactive map below and posted signs for details and updates.

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov

 
Beaver Street Interceptor Rehabilitation/Replacement Project
This project consists of the replacement and repair of Franklin's largest piece of sewer infrastructure, originally constructed in 1914.

This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.

Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe
here (select Beaver Street Interceptor from the list).

Beaver Street Interceptor - construction & detours for the week of May 28 - May 31, 2024
Beaver Street Interceptor - construction & detours for the week of May 28 - May 31, 2024

Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor


No comments:

Post a Comment