Beaver Street Interceptor (BSI)
BSI Construction Update for the Week of July 22!
Monday (7/22) - Friday (7/26) the construction crew will be working on West Central Street from Rt. 140 towards the BJ's plaza between the hours of 7am - 4pm. Expect lane closures as the work progresses.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation of the pump station within the sheet pile area.
Please reference the interactive map below and posted signs for details and updates.
Beaver Street Interceptor: Construction update for week of July 22, 2024
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914