Updates to Beaver St. Interceptor Project for Week of May 19 - 23, 2025
Saturday, November 16, 2024
Beaver Street Interceptor (BSI) Project: construction updates for Week of Nov 18 - Nov 22
Beaver Street Interceptor (BSI) Project
Beaver Street Interceptor (BSI) Project: construction updates for Week of Nov 18 - Nov 22 |
BSI Construction Update for the Week of November 18th!
Monday (11/18) - Friday (11/22): The construction crew will be on Grove Street in the area of 25 Grove Street (near Forge Hill Rd.) working on the Grove Street sewer siphon. All work will occur on the side of the road with little to no traffic impacts.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation walls.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: construction updates for Week of Nov 18 - Nov 22 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Saturday, November 9, 2024
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of November 11
Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of November 11th!
Thank you to all the Veterans for your service!
Monday (11/11) - Wednesday (11/13): Beaver Street from RT. 140 (West Central Street) to the Franklin Recreation Center will be closed, see interactive map for location.
The road closure will be from 7am to 4pm, Monday thru Wednesday.
Those needing to access the businesses/properties and the Recycling Center located on that section of Beaver Street will be detoured over to Grove Street. Starting Monday 11/11, those needing access to Franklin Glass and the Franklin Recreation Center will enter Beaver Street via Rt. 140. Please follow all posted detour signs and be prepared for delays. Note that all businesses on Beaver Street remain open and accessible, please follow posted signs for access.
On Thursday 11/14 and Friday 11/15, the Construction Crew will be on Rt. 140 in front of Dunkin' Donuts. A single lane closure will be in place between 7am to 4pm.
Also on Friday 11/15, the Construction Crew will be in front of 664 Old West Central. Old West Central/Pond Street will be closed starting at Rolling Ridge to where Old West Central and Pond Street meet. The detour via Hilltop and Rolling Ridge will be in place. Please use caution in this area and follow the posted speed limit signs.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation walls.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of November 11 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Saturday, November 2, 2024
Beaver Street Interceptor Project Construction Update for Week of Nov 4 - 8 (Beaver St detour continues)
Beaver Street Interceptor (BSI) Project
Beaver Street Interceptor Project Construction Update for Week of Nov 4 - 8 (Beaver St detour continues) |
Monday (11/4) - Friday (11/8): Beaver Street from RT. 140 (West Central Street) to the Franklin Recreation Center will be closed, see interactive map for location. The road closure will be from 7am to 4pm, Monday thru Friday.
Those needing to access Beaver Street and the businesses/properties located on that section of Beaver Street will be detoured over to Grove Street. Please follow all posted detour signs and be prepared for delays. Note that all businesses on Beaver Street remain open and accessible, please follow posted signs for access.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation walls.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor Project Construction Update for Week of Nov 4 - 8 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Saturday, October 26, 2024
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of October 28
Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of October 28th!
Monday (10/28) - Friday (11/1): Beaver Street from RT. 140 (West Central Street) to the Franklin Recreation Center will be closed, see interactive map for location. The road closure will be from 7am to 4pm, Monday thru Friday.
Those needing to access Beaver Street and the businesses/properties located on that section of Beaver Street will be detoured over to Grove Street. When the contractor is able to, they will open up one way traffic from RT. 140 towards Grove Street. Please follow all posted detour signs and be prepared for delays.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation.
On Tuesday October 29th, a small concrete pour is scheduled in the morning, prior to activities starting at the Recreation Center.
Please reference the interactive map below and posted signs for details and updates.
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of October 28
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Saturday, October 5, 2024
Beaver Street Interceptor (BSI) Project: construction updates for week of Oct 7 to 11
Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of October 7th!
Monday (10/7) - Tuesday (10/8): There will be a construction crew working in the area of West Central St and Forge Pkwy at the entrance to BJ's between the hours of 7am-4pm. Please follow detour signs.
Tuesday (10/8) - Friday (10/11): There will also be a construction crew working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. Grove Street will be open and reduced to a single lane.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement of the pump station foundation.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: construction updates for week of Oct 7 to 11 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Saturday, September 28, 2024
Beaver Street Interceptor (BSI) Project: Construction detours for week of Sep 30, 2024
Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of September 30th:
Monday (9/30) - Friday (10/4): There will also be a construction crew working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. Grove Street will be open and reduced to a single lane.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: Construction detours for week of Sep 30, 2024 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.
Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe here (select Beaver Street Interceptor from the list).
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Saturday, September 14, 2024
Beaver Street Interceptor Project: construction update for week of 9/16 to 9/20
Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of September 16th!
Monday (9/16) - Friday (9/20): The construction crew will be working on West Central St between Rt 140 and Forge Pkwy between the hours of 7am-4pm. West Central St will be closed in both directions. Please follow posted detour signs for directions.
Monday (9/16) - Friday (9/20): There will also be a construction crew working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. Grove Street will be open to one way traffic only from RT. 140 towards Forge Hill Road.
Please follow posted detour signs for directions.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation.
Please reference the interactive map below and posted signs for details and updates.
Beaver Street Interceptor Project: construction update for week of 9/16 to 9/20
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914.
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Thursday, September 12, 2024
Road Closure Information for Franklin/Norfolk - Lawrence St for Sep 16 through 18
For additional information, including a road closure map, please view the images below
![]() |
Road Closure Information |
![]() |
Lawrence St for Sep 16 through 18 |
Shared from -> https://www.franklinma.gov/public-works/news/road-closure-916-918-norfolk-and-franklin
Saturday, September 7, 2024
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of Sept 9 - Sept 13, 2024
Beaver Street Interceptor (BSI) Project
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of Sept 9 - Sept 13, 2024 |
Monday (9/9) - Thursday (9/12): The construction crew will be working on West Central St between Rt 140 and Forge Pkwy between the hours of 7 am - 4 pm. West Central St will be closed in both directions. Please follow posted detour signs for directions.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: Construction Update for the Week of Sept 9 - Sept 13, 2024 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
Tuesday, July 23, 2024
Beaver Street Interceptor: Construction update for week of July 22, 2024
Beaver Street Interceptor (BSI)
BSI Construction Update for the Week of July 22!
Monday (7/22) - Friday (7/26) the construction crew will be working on West Central Street from Rt. 140 towards the BJ's plaza between the hours of 7am - 4pm. Expect lane closures as the work progresses.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation of the pump station within the sheet pile area.
Please reference the interactive map below and posted signs for details and updates.
Beaver Street Interceptor: Construction update for week of July 22, 2024
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914
Interested in receiving email updates regarding the Beaver Street Interceptor Rehabilitation/Replacement Project? Please subscribe here (select Beaver Street Interceptor from the list).
Monday, June 3, 2024
Jordan Rd closed on June 5 weather permitting
From the DPW: Jordan Road paving work to continue on Wednesday, June 5 - weather permitting
Tuesday, May 7, 2024
Beaver Street Interceptor: construction and detour update
Beaver Street Interceptor
Beaver Street Interceptor: construction and detour update |
The dead end section of Old West Central serving Ledgewood Condominiums and Franklin Crossing will continue to be closed at Tri-County Drive. Those residents should continue to follow the posted signs for directions on exiting and entering.
Starting on Thursday May 9th, construction work will move onto Rt. 140 in front of the Dunkin Donuts, expect lane closures and traffic delays due to active roadwork.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor: construction and detour update |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor
Saturday, April 13, 2024
Beaver Street Interceptor: traffic detour update for week of April 15, 2024
Beaver Street Interceptor
Continuing on Monday, April 15th, the dead end section of Old West Central serving Ledgewood Condominiums and Franklin Crossing will continue to be closed at Tri-County Drive. Those residents will continue to use the right-hand turn only detour onto Rt 140 by the Dunkin Donuts.
This detour will be in place Monday-Friday 7AM thru 4PM.
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914.
Saturday, April 6, 2024
Beaver Street Interceptor - detour update for week beginning April 8, 2024
Beaver Street Interceptor
The contractor has made great progress this week, so starting Monday April 8th Old West Central between Rt. 140 to Pond Street will be back open to two way traffic. The dead end section of Old West Central serving Ledgewood Condominiums and Franklin Crossing will continue to be closed at Tri-County Drive. Those residents will continue to use the right hand turn only detour onto Rt 140 by the
Dunkin Donuts.
For Monday only, the entrance to Tri-County Drive at Old West Central will remain closed. All Tri-County traffic will need to enter and exit via the Pond Street Entrance.
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
![]() |
Interactive construction detour map & updates |
originally constructed in 1914.
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor
Saturday, March 30, 2024
Beaver Street Interceptor: Detour update for week of April 1
Beaver Street Interceptor
As construction continues within the Old West Central St area, a larger detour will be in place. Anticipated to run Monday through Friday between 7:30am to 4:00pm from Monday April 1st through Friday April 12th, this primarily impacts local and school traffic. Please see included details which clarifies access.
![]() |
Beaver Street Interceptor: Detour update for week of April1 |
We appreciate the public's continued support and understanding and will continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
Monday, March 25, 2024
Reminder: detour starting Monday, March 25 for Beaver St interceptor construction
![]() |
Reminder: detour starting Monday, March 25 |
Saturday, March 9, 2024
New Detour for the Beaver Street Interceptor Construction for week of March 11
Beaver Street Interceptor
As construction continues within the Old West Central St area, a new detour will be in place. Anticipated to run from Monday March 11th through Friday March 15th, this primarily impacts local traffic on the dead end section of Old West Central St. Please see included details which clarify access. We appreciate the public's support and understanding and will continue to communicate as work progresses.
![]() |
New Detour for the Beaver Street Interceptor Construction for week of March 11 |
Please see our interactive map below for more details.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.
Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe here (select Beaver Street Interceptor from the list).
Wednesday, December 13, 2023
Beaver Street Interceptor: Construction Detour begins Dec 14
Beaver Street Interceptor -> CONSTRUCTION UPDATE
TRAFFIC DETOUR ALERT: Starting Thursday December 14th,
the area of Old West Central St., Pond St., and Rolling Ridge Rd.
will be impacted by a construction detour.
Access to this area may look different as work continues
but LOCAL BUSINESSES REMAIN OPEN!
Please visit our interactive construction map for details
https://apexmapping.maps.arcgis.com/apps/instant/sidebar/index.html?appid=8aa942ac0c4c4942826c3bf83ef253ae
We will update and communicate regularly via social media,
our dedicated email list, and the construction map.
Please see our interactive map below for more details.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
![]() | ||
Old West Central St., Pond St., and Rolling Ridge Rd. | will be impacted by a construction detour |
This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.
Beaver Street Interceptor Rehabilitation/Replacement Project
originally constructed in 1914
Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe here (select Beaver Street Interceptor from the list).
History
The Beaver Street Interceptor (BSI) was originally constructed in 1914 and discharged to the former Franklin Wastewater Treatment Plant on Pond Street (aka, the sewer beds). Currently, the BSI conveys over 70% of the Town's sewage with an average daily flow (ADF) of approximately 1.5 million gallons per day (MGD) of sewage flow through the pipeline. The interceptor includes 59 manholes and approximately 2.3 miles (11,932 LF) of 16-inch to 24-inch cast iron (CI) pipe, reinforced concrete (RC) pipe, and vitrified clay (VC) pipe. The BSI extends from the intersection of Cottage Street and Union Street to the easement behind Pond Street, near the Interstate 495/Route 140 interchange, where it discharges to the Mine Brook Interceptor. Due to its age, the risk and consequence of failure, and the percentage of the Town's sewer flows conveyed by the interceptor, the BSI is considered Franklin's most critical sewer asset.
The BSI, constructed in 1914, has been in continuous service for 108 years. Other than routine maintenance, no improvements to the interceptor have been made since its construction. Since 2003, the Town has contracted for cleaning, internal investigation, and condition assessment of the BSI on a recurring 5-year basis. Extensive manhole inspections and cleaning and closed-circuit television (CCTV) inspection of the pipes were last completed in 2013 and 2014, respectively. Results of these investigations have shown signs of increasing deterioration and worsening conditions of the pipes and manholes, most notably increased tuberculation, cracks, manhole and pipeline infiltration, and root intrusion.
Rehabilitation/Repair Project Description
The Project is located in the Town of Franklin, MA in Norfolk County. The current interceptor is in need of replacement. Therefore, the Town proposes rehabilitation, replacement, and general improvements to the interceptor as well as a new pump station on the property at 275 Beaver Street, Franklin, MA. The proposed project provides the most cost-effective, long-term solution to the BSI's capacity and structural deficiencies, human health and environmental risks, accessibility and operation and maintenance challenges, by abandoning and rerouting sewers in the most risk-prone and problematic, inaccessible areas. The work of the Project to reroute sewers is being undertaken, in part, to move sewers out of wetland resource areas at the same time as making other improvements.
The Project includes the following key components:
- New 6 MGD Beaver Street Pump Station and 4,000 LF of 18-inch Force Main from the pump station to discharge at Pond Street.
- Rehabilitation of 6,100 LF of BSI using Cured in Place Pipe Lining (CIPPL)
- Installation of 6,000 LF of new gravity sewers
- The work will take place at 5 MBTA/Keolis Railroad Crossings including 3 pipe replacements using jack and bore technique and 2 pipe rehabilitation locations using CIPPL.
- Abandonment of BSI from Panther Way to Franklin Village Plaza and Route 495 crossing
For additional information see links below:
Alternative Analysis:
Beaver St Interceptor Alternatives Analysis
Appendix A-Manhole Inspection Logs-May 2013
Appendix B-CCTV Inspection Logs-August 2014 to September 2014
Appendix C-Hydraulic Model Technical Memorandum
Appendix D-BSI Replacement-Franklin Town Council Meeting Presentation-10/21/20
Appendix E Project Cost Estimates
Presentations:
Beaver Street Interceptor Public Outreach Meeting October 26, 2023
Interceptor Town Council Presentation Update June 2022
Interceptor Alternatives Analysis Town Council Presentation 10/21/20
Notice of Intent-Conservation Commission:
Notice of Intent Packet-Franklin Conservation Commission Submittal
Project Site Overview Figure
Media Coverage:
What is the Beaver St Interceptor? Why does it need to be replaced? -TUESDAY, JULY 26, 2022 (https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor )
Schedule:
December 21, 2022 - Advertise for Bids
https://www.franklinma.gov/purchasing/bids/beaver-st-interceptor-rehabilitationreplacement-and-new-beaver-st-pump-station)
(https://www.milforddailynews.com/public-notices/notice/12/21/2022/bids-beaver-street-pump-station-legal-2022-12-21-the-milford-daily-news-massachusetts-0cc175)
March 8, 2023 - Bid Opening
June 15, 2023 - Anticipated Contact Award
Fall/Winter 2023 - Anticipated Construction Start
Summer 2026 - Anticipated Construction Completion
You can unsubscribe here.
Friday, October 25, 2019
Franklin Residents: Beaver St. Detour October 25 - 27
"Beaver Street will be closed to through traffic at the railroad tracks from Friday evening 10/25 through Sunday afternoon 10/27.
Motorists attempting to access the Beaver Pond athletic fields and the Town of Franklin Transfer station will need to access Beaver Street via Grove Street."
![]() |
Franklin Residents: Beaver St. Detour October 25 - 27 - alternate route |
![]() |
Franklin Residents: Beaver St. Detour October 25 - 27 |
This was shared from the Town of Franklin page
https://www.franklinma.gov/home/news/beaver-st-detour-october-25-27
Subscribe for your own alerts/notifications via email
https://www.franklinma.gov/subscribe