Beaver Street Interceptor (BSI) Project
BSI Construction Update for the Week of September 30th:
Monday (9/30) - Friday (10/4): There will also be a construction crew working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. Grove Street will be open and reduced to a single lane.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation to get the final grade depth for the pump station foundation.
Please reference the interactive map below and posted signs for details and updates.
![]() |
Beaver Street Interceptor (BSI) Project: Construction detours for week of Sep 30, 2024 |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.
Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe here (select Beaver Street Interceptor from the list).
Read more -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project
No comments: