Wednesday, July 8, 2015

Downtown Project Update # 6


Work will continue with sidewalks and curbing from School to Pleasant Street over the next few weeks. 
They anticipate repaving the roadway from the Church to Moore Avenue starting in a few weeks. 
Following that they will mill and overlaying portions on Emmons street. Following that work will begin on West Central Street. More information will be available for the next update. 
In the meanwhile they will be installing the mast arms for the traffic control at Emmons and West Central and at the Bridge. Further they will continue to install the bases of the street lights. 
If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer Michael, Maglio at 508-553-5500 or my office at 508-520-4949

curbing work underway along Main St
curbing work underway along Main St