Beaver Street Interceptor: Construction update for Week of Aug 5 to Aug 9

Beaver Street Interceptor (BSI)

 
Beaver Street Interceptor:

BSI Construction Update for the Week of August 5!

Monday (8/5) - Friday (8/9) the construction crew will be working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm.  Traffic turning onto Grove Street from Rt. 140 will be detoured over to Beaver Street via Rt. 140.  Please follow posted detour signs for directions.

On Monday 8/5 - West Central Street between Rt 140 and Pond Street (area behind Starbucks) a company will be testing the newly installed sewer mains. No traffic impacts are expected.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with installation of steel beam bracing on sheet piles. 

Please reference the interactive map below and posted signs for details and updates.

Beaver Street Interceptor: Construction update for Week of Aug 5 to Aug 9
Beaver Street Interceptor: Construction update for Week of Aug 5 to Aug 9

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov

 
Beaver Street Interceptor Rehabilitation/Replacement Project
This project consists of the replacement and repair of Franklin's largest piece of sewer infrastructure, originally constructed in 1914.