Beaver Street Interceptor Project (BSI)
Monday (8/19) - Friday (8/23) the construction crew will be working on Grove Street from Rt. 140 south towards the MBTA train tracks between the hours of 7am - 4pm. There will be limited lane closures on Grove Street during this time please follow posted detour signs for directions.
Also, there will be a crew working on Old West Central Street Thursday (8/22) and Friday (8/23) connecting the sewer services for house no. 650 & 657. A limited detour on Rolling Ridge Rd. will be in place during this time -- please follow posted detour signs for directions.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with excavation and the installation of steel beam bracing on sheet piles.
Please reference the interactive map below and posted signs for details and updates.
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
This site and map will be updated on a weekly basis to convey upcoming construction activities for the Beaver Street Interceptor (BSI) Construction project.
Interested in receiving email updates regarding the
Beaver Street Interceptor Rehabilitation/Replacement Project?
Please subscribe here (select Beaver Street Interceptor from the list).
Shared from -> https://www.franklinma.gov/water-sewer-division/pages/beaver-street-interceptor-project