Beaver Street Interceptor (BSI) Project

 
logo
 
 

Beaver Street Interceptor (BSI) Construction Update for the Week of January 6th!

Monday (1/6) - Friday (1/10): The construction crew will be preparing for and starting the jack and bore trenchless installation of the sewer under Rt. 140.  The work will be occurring off the road at 38 Pond Street and within the Franklin Village Mall Area.  No traffic impacts are expected. 

Wednesday (1/8) - Friday (1/10):  The construction crew will be conducting test pits and preparatory work for the future jack and bore locations on Fisher Street and Grove St.  Limited traffic impacts are expected.  Motorists are asked to please follow the directions of the detail officers.

At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete placement.

Please reference the interactive map below and posted signs for details and updates.

Construction Update for the Week of January 6
Construction Update for the Week of January 6

We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.


BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov


No comments:

Post a Comment