Beaver Street Interceptor (BSI) Project Construction Updates: Monday (11/24) through Tuesday (11/25)

Beaver Street Interceptor (BSI) Project
Beaver Street Interceptor (BSI) Project
No work 11/26 through 11/28 - HAPPY THANKSGIVING!

RT. 140 (West Central Street) Lane Closure Alert  - Monday Night (11/24) 7PM to 5AM and Tuesday (11/25) during the day 8AM to 3PM
Monday night, November 24 from 7PM to 5AM and Tuesday, November 25 from 8AM to 3PM the Contractor will continue with the installation of the sewer force main within RT. 140 (West Central Street). The work will be contained within the southbound lane from Burger King to Beaver Street. During this time there will be evening lane closures on RT. 140. Please use caution when traveling in this area and follow all posted signs.
Grove Street Closed Notice - Monday 11/24
Grove Street will be closed at the MBTA train tracks on Monday 11/24 between the hours of 7am and 4pm. 
Traffic turning onto Grove St from Rt. 140 will be detoured over to Beaver Street via Rt. 140. Please follow posted detour signs for directions. The area will be open to Local Traffic only to access the businesses and properties on Grove Street between Forge Hill Road and Rt. 140.
Beaver Street Pump Station
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with construction of the exterior building structure, internal building component installation, and final site work.