Wednesday, October 14, 2015

Downtown Project Update # 12



The paving of Emmons Street, West Central Street and Summer Street are now scheduled for the week of October 26th.

The crosswalk on West Central Street for Dean College near the Davis Thayer School will move closer to the intersection where the new traffic signal will be installed and temporary stop signs will be erected at the end of Emmons Street until the lights are installed.

They will continue to construct sidewalks on West Central Street.

The plan is to put in new curbs and sidewalks on East Central Street from Cottage Street to Summer
Street this fall. 

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at
508-520-4949.

new sidewalks and curbing on West Central St
new sidewalks and curbing on West Central St

No comments:

Post a Comment