School Committee - building committee update

d. FHS Building Update 


Tom Mercer,  Sean Fennel

Daedelus worked on the Annie Sullivan School, Fire Station, Senior Center and Horace Mann projects. Have now been selected to work on the FHS renovation project.

22 firms showed up for a walk through of the high school
9 submitted proposals for the first phase of the project

Projected timeline, best guess at this point
midway through architect selection
July 13th going before the MSBA board (target date)
Town will have option to interview firms at that meeting, interviews would be scheduled later
Coming out of the interviews would be a leading firm and contract negotiations by mid-August

MSBA Board needs to vote on the feasibility study, which is targeted for March 2011
Schematic design approval is required and targeted in Sept/Oct 2011
Then within 120 days of the MSBA approval, the Franklin voters need to approve their portion (i.e. Nov 2011 vote for the debt exclusion as mentioned earlier)

MSBA Board and three designated representatives to chose the architect
One each from the School Dept, Town, and School Committee
This group would be the ones to conduct the interviews and make the final decision on the architect

Q - when and where would the interviews be?
Interviews would be held two weeks later (after the July 13th meeting), in Boston, in the same room
All meetings are public

Q - are you reviewing the proposals now?
Yes, they are being reviewed. The Board is responsible for the decision on the proposals. The MSBA Board has 12 members plus the 3 designated reps as outlined above.

Q - when would be the debt exclusion?
According to the timeline, likely Nov 2011

Q - when would the construction be completed?
Too early to tell, we don't know what the work will be at this point