Thursday, June 11, 2015

Downtown Streetscape Project Update #4

From Franklin's Town Administrator Jeff Nutting

Downtown Project Update #4


June 9, 2015



The expected work over the next two weeks will involve sidewalk work on Main Street from Emmons up to Pleasant Street, except the sidewalk next to the Town Common and sidewalk work on Emmons Street between Main and West Central Street.

new sidewalks being installed along Main St
new sidewalks being installed along Main St

The contractor plans to start road work between Main and Pleasant Street including High Street on or after June 15th

Further he expects to start sidewalk work on West Central Street between Emmons and Union Street on both sides and the sidewalk along West Central Street on the Fire Station side.

The sidewalk on the other side of West Central will be done after all the old utility poles have been removed.

The specific dates for the above mentioned work may vary depending on weather and crew availability

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer Michael, Maglio at 508-553-5500 or my office at 508-520-4949.


No comments:

Post a Comment