Downtown Project Update #10

Note the dates added in parenthesis ( ) are my interpretation of the schedule. This was posted on Wed 9/17 and by the time this gets out and around the reference points can change.

Next Wednesday they will be setting the curbs on West Central Street (they were waiting on the subcontractor).  (9/24)
Mid to late next week they will be line striping the new top that they are putting down this week.  (approx 9/24)
At the end of next week or into the following week the landscapers will be spreading loam and seeding in the area that has been paved and completed.  (approx 9/25 through 10/2)
Starting tomorrow and into next week they will be finalizing walk ways between Moore Ave and Pleasant Street.  (9/18 through 9/25)
The week after next they will be paving Emmons Street and Summer Street, possibly at night.  (approx week of 9/28)
In about two weeks they will be working in front of the Fire Station entrance. 
They are not excavating any more sidewalks on West Central Street for now.The sidewalk widening on Main Street will be done when the subcontractor gets back, in the next few weeks. 
We are waiting on National Grid to move a few telephone poles. 
If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Jeffrey Nutting, Town Administrator at 508-520-4949.