"Phase 8 - Sewer Lining Project Starts Monday November 25th.
You will see National Watermain trucks conducting cleaning and CCTV inspection of the sewer lines on the following streets on 11/25 & 11/26 and 12/2 thru 12/6 :
Sewer Lining Project work scheduled along Pine St, Mary Anne Dr & Stanwood Dr
Sewer Lining Project along Pine St, Mary Anne Dr & Stanwood Dr
  • Pine Street (Pond St to Town of Bellingham Line)
  • Mary Anne Drive
  • Stanwood Drive
During this part of the lining there will be minimal disruption to sewer service. If you experience any issues please call the DPW at 508-553-5500.
The crew will then be back out in the same locations starting in early January to conduct the sewer main lining work. This work will help to improve the structural integrity of our sewer system and reduce groundwater intrusion which reduces our bill from the Charles River Pollution Control District"