Beaver Street Interceptor (BSI) Project
Beaver Street Interceptor (BSI) Project |
HAPPY THANKSGIVING!! (NO WORK 11/28 & 11/29)
Monday (11/25): The construction crew will be on Grove Street in the area of 25 Grove Street (near Forge Hill Rd.) working on the Grove Street sewer siphon. All work will occur on the side of the road with little to no traffic impacts.
Tuesday (11/26) - Wednesday (11/27): The construction crew will be on Rt. 140 and Old West Central working on testing of the new sewer main. Old West Central will be a one lane road in and out. Rt. 140 will have a single lane closure. Please follow all posted detour signs and be prepared for delays.
At the Franklin Recreation Center, the construction of the new Beaver Street Interceptor Pump Station will continue with concrete form placement and rebar tying for the pump station foundation walls.
Please reference the interactive map below and posted signs for details and updates.
https://apexmapping.maps.arcgis.com/apps/instant/sidebar/index.html?appid=8aa942ac0c4c4942826c3bf83ef253ae |
We appreciate the public's continued support and understanding and will
continue to communicate regularly via social media, our dedicated email list, and the construction map below as work progresses.
BEAVER STREET INTERCEPTOR HOTLINE: 508-553-5526
(PLEASE LEAVE A MESSAGE AND WE WILL RETURN YOUR CALL)
EMAIL: BSI-info@franklinma.gov
originally constructed in 1914.